1) widen the paved road from 24 feet to 32 feet, 2) lower the profile of two hills to improve sight distance and construct a 32 feet wide roadway, 3) replace one double box concrete culvert with a double box pre-cast concrete culvert with headwalls, wingwalls and guardrails, 4) pave roadway with asphalt concrete from Shawn Lane to Allendale Road, and 5) scarify the existing gravel roadway surface north of Allendale Road, and regrade roadway with granular materials. Bids must be on a unit price basis
  Addendum 1 (click to expand/collapse)
Download section as a Zip file free of charge
Name Size
Timm Addenda 1 signed 446.9 KB
Timm Road - X Section_2020.04.10 2.6 MB
  Addendum 2 (click to expand/collapse)
Download section as a Zip file free of charge
Name Size
Timm Rd Addendum 2 Attachment A Revised Bid Schedule 142.8 KB
Timm Road Addendum 2 Signed 1.2 MB
Timm Road Revised Plan Sheet 12.2 MB
Timm Road Roadway Excavation Takeoff 315.5 KB